Check for OEM repair guidelines in order to determine if the application should be bond only, weld bond or rivet bond and then proceed with the proper Fusor® Standard Operating Procedure.
1. Remove the old panel using care not to damage remaining panels.
2. Clean any remaining adhesive or sealers from bonding flanges.
3. Using new panel as a guide, confirm all bonding flanges are undamaged and mate up with the replacement panel. Make repairs as needed.
4. Prepare for the panel installation by having all necessary clamping devices on hand and determine if panel will be 100% bonded or if a butt-joint exists which will require MIG-welding or MIG-brazing.
5. Prepare bonding flanges on replacement panel to receive adhesive.
6. Clean all bonding flanges with solvent.
Tech Tips:
7. Prepare adhesive for application by purging the cartridge and leveling the plungers before installation of the mixing nozzle and running out a bead to ensure a homogeneous mix.
8. Apply adhesive to the bonding area.
9. Install and clamp the panel in position.
10. Release the clamps once the adhesive has reached its handling strength noted on the product label.
Tech Tips:
11. Before the adhesive begins to cure: